top of page
Search

Works Commence at Hurstpierpoint College

Works are commencing at great pace at Hurstpierpoint College with the site set up and installation of the piling mat complete. The team are now driving the 98 piles into position ahead of the drainage and groundworks commencing and arrival of a 18-meter crane next week.


Working in collaboration with Miller Bourne, Wenham O’Brien, HOP and RED Engineering, MCS has been appointed to design and construct a Swimming Pool building that provides a 25-metre 6 lane swimming pool, conforming to ASA competition standards.


The building, with many sustainability features, will also provide: changing rooms with toilets and showers; disabled changing rooms, store room and reception area.



bottom of page