St Josephs Catholic School
Hanwell, Middlesex
Contract Value
£3.5 million
1/7
Contract Admnistrator
Synergy CPC LLP
Architect
DHP (UK) LLP
Contract Duration
43 weeks
Completed
2016
Project Description
A phased project to create a new standalone 6 classroom teaching block with a green roof.
All works were carefully phased to allow the school to remain fuilly operational whist extensions to the hall, kitchen and classroom extensions were carried out in the main school. As part of the project there were associated internal alterations and extensive external works.