Manby Lodge Infant School
Weybridge, Surrey
Contract Value
£2.1 million
Contract Admnistrator
Surrey County Council
Architect
NPS Group
Contract Duration
73 weeks
Completed
2016
Project Description
The works involved a major expansion of the school on a very tight and logistically challenging site.
The layout and access of the school was completely changed; retained buildings were altered and extended, the old buildings and the original school were demolished and were replaced by a new large single storey extension, a new large two-storey block and extensive buried drainage and external works reconfigurations.
All the works had to be completed in seven pre-agreed sectional handover phases some of which ran concurrently with others, whilst the school remained operational. Very little of the original school remained at completion of the project.
Working in conjunction with Surrey County Council and the staff at the school MCS were able to deliver this logistically difficult project to the agreed programme and budget. The school were very happy with the works and MCS has received glowing references from the project managers.
This project was awarded to MCS through a competitive tender process as we were approved as one of the 'Select Panel Contractors' for the SCC Primary School build programme.